Data Centre, Waltham Cross

Frost ProtectionTemperature Maintenance
Aerial view of a large industrial complex with multiple buildings and parking lots, surrounded by a residential area and greenery under a cloudy sky.
Overview

Frost protection for a hyperscale data centre

A Raychem trace heating system protecting external pipework from freezing and holding domestic hot water at temperature, across a facility that never goes offline.
Process chilled water and domestic cold water both run outside the building envelope, where a hard frost can take critical cooling offline. Self-regulating cable and line-sensing control hold those circuits above freezing without manual intervention, while the same system maintains domestic hot water so it reaches outlets at temperature. The result is a building service that looks after itself through the winter.
8,000m+
Self regulating cable
109
Independent Circuits
33
Acre Site
3 yrs
Programme
Delivered over a two-year construction programme, the installation was coordinated alongside the mechanical and electrical works to meet the overall build schedule. It comprised over 10,000 metres of Raychem heating cable across more than 100 independent circuits, spanning all 45 floors including roof plant and external services. Every circuit was inspected, tested, and commissioned before handover, with full as-installed drawings and documentation provided. The completed system delivers reliable heat maintenance, frost protection, and grease waste temperature maintenance throughout the building, fully integrated with its mechanical and electrical services.
Client
Undisclosed
Services
Frost Protection, Temperature Maintenance
Location
Waltham Cross, Hertfordshire
Duration
3 years
Frost Protection
Prevent damage, maintain operational reliability and minimise disruption caused by freezing conditions.
Temperature Maintenance
Ensuring systems operate efficiently, safely, and year-round